    Yes, there is a print function in factro. You can print the project views

    1. work breakdown structure and
    2. Gantt

    as a PNG or PDF file. For this, go to the settings wheel within the respective project view and click on “Print”. At this point in the Gantt chart, you can specify how wide or narrow the printout should be, so that the scaling corresponds to your wishes.

    You will find the "Print" button via the settings wheel
    You will find the “Print” button via the settings wheel